Key Tasks and Responsibilities:
– Perform schedule analysis using Project Management software including Primavera P6, Deltek Fuse & Risk, and Microsoft Project
– Support project baseline creation during the project initiation and setup phase
– Facilitate detailed multi-discipline scope reviews
– Provide project schedule support and mentor junior planners as required
– Develop and maintain logically linked level 3 and level 4 activity schedules, for marine scope installation projects in the Oil and Gas Industry (pipelines, subsea, platforms, HDD), according to precedence flow planning, using best practices
– Produce workforce histograms and progress and quantity curves in connection with the schedules
– Maintain and review the sequence of Engineering, Procurement, Fabrication, Construction, Hook-Up, and Commissioning, and other operations for control of critical path and overall project durations
– Elevate and expedite operations that are delaying the schedule and analyze changes to the schedule to meet unforeseen conditions
– Create and Monitor schedule compliance, key performance, factors, and provide analysis of variations to baseline data
– Identify factors, both current and potential, that may delay the schedule. Assess actions for recovery and improvement and analyze changes to the schedule to meet unforeseen conditions